If you invoice a US federal agency under a contract that includes the standard FAR clause 52.232-25, payment is due on the later of two dates: the 30th day after the agency’s billing office receives a proper invoice, or the 30th day after the agency accepts the work. Pay late and the agency owes you interest without you asking. A defective invoice resets the whole clock, which is why the details below matter.
This post covers contracts with the US federal government only. It does not cover state or local agencies, which have their own prompt payment laws, and it does not cover private clients. Read your own contract, because the clause can be changed or replaced.
What the 30 days actually measure
The wording comes from the FAR clause 52.232-25, Prompt Payment. The due date is the later of:
- The 30th day after the designated billing office receives a proper invoice.
- The 30th day after the Government accepts the supplies or services.
For the sole purpose of working out interest, the clause treats acceptance as happening on the 7th day after you deliver, unless the contract says otherwise or there is a disagreement over quantity, quality or compliance. If the billing office forgets to stamp the receipt date, the due date becomes the 30th day after the date on your invoice, provided the invoice is proper and nothing is in dispute.
Some goods have shorter deadlines. The clause sets payment for meat and fish at no later than the 7th day after delivery, and for perishable agricultural commodities and dairy products at no later than the 10th day.
| Event | What the clause says |
|---|---|
| Standard due date | Later of 30 days after proper invoice or 30 days after acceptance |
| Constructive acceptance (interest only) | 7th day after delivery, unless contract says otherwise |
| Defective invoice | Returned within 7 days of receipt, with reasons |
| Meat and fish | No later than the 7th day after delivery |
Source: FAR 52.232-25 (Acquisition.GOV).
What makes an invoice “proper”
The agency’s obligation only starts when the billing office has a proper invoice. The clause lists what one must include. If yours does not comply, the billing office will return it within 7 days of receipt and tell you why.
| Proper invoice item | Notes from the clause |
|---|---|
| Your name and address | Required |
| Invoice date and number | Date it as close as possible to when you mail or send it |
| Contract number or other authorization | Include order number and line item number |
| Description, quantity, unit of measure, unit price, extended price | For each item delivered |
| Shipping and payment terms | Includes prompt payment discount terms |
| Payment address | Must match the contract or a proper notice of assignment |
| Contact for a defective invoice | Name, title, phone and mailing address where practicable |
| Taxpayer Identification Number | Only if the contract requires it |
| EFT banking details | On the invoice only if the contract requires it, otherwise submitted separately |
| Anything else the contract requires | For example evidence of shipment |
Source: FAR 52.232-25(a)(3).
The practical lesson is that the missing contract number is the easiest way to lose weeks. The same logic applies to every client with a purchasing department, and our guide to chasing overdue invoices without sounding awkward covers the follow-up once an invoice is in the right hands.
When the agency owes you interest
The clause says the payment office will pay an interest penalty automatically, without a request from you, if payment is late and all three conditions apply:
- The billing office received a proper invoice.
- The Government processed a receiving report or other documentation authorizing payment, with no disagreement over quantity, quality or compliance.
- For a final invoice, the amount was not subject to further contract settlement actions.
Interest runs from the day after the due date through the payment date, at the rate in effect on the day after the due date, under the Office of Management and Budget rules in 5 CFR 1315.10. Interest still unpaid after any 30 day period is added to the principal for up to one year.
If the agency owes at least $1 in interest and does not pay it within 10 days after paying the invoice, you can claim an additional penalty. You must make a written demand, postmarked no later than 40 days after the invoice amount was paid. Your demand has to say that interest is due under a specific invoice, attach a copy of that invoice, and state that you received the principal and when. The size of the additional penalty is set by OMB regulation.
Where the rules stop
Federal law does not force an interest penalty when payment is held up by a real dispute over the amount or over compliance with the contract. 31 U.S.C. 3907 also says an interest penalty does not keep accruing after you file a claim under the Contract Disputes Act process, or for more than one year. See 31 U.S.C. 3907.
Subcontractors have a separate clause. FAR 52.232-40 says that within 15 days after a prime contractor receives accelerated payments from the Government, it must pay its small business subcontractors accelerated payments, to the maximum extent practicable, after receiving a proper invoice and the other required documents. Check whether your subcontract flows that clause down.
Send a proper invoice every time
Everything above rests on one document. A BillyPaid invoice gives you a clean numbered layout with line items and payment terms, so you can check it against the list above before you send.