Under the Housing Grants, Construction and Regeneration Act 1996, a UK construction contract has to set a due date and a final date for payment, and it has to require a payment notice within five days of the due date. A payer who wants to pay less than the notified sum must send a pay less notice, in time and with the calculation. If the payer sends no payment notice, you can send your own, and the sum in it becomes the notified sum the payer must pay unless a valid pay less notice follows.

This post summarizes sections 109 to 112 of the Housing Grants, Construction and Regeneration Act 1996 as published on legislation.gov.uk and checked on 3 November 2026. The Act applies to construction contracts in England, Wales and Scotland, but some contracts are excluded by orders, including the Construction Contracts (Exclusion) (Wales) Order 2023. Whether your work counts as construction operations under the Act is a legal question. Read your contract and take advice before you rely on this.

Stage payments, due dates and final dates

Section 109 says that a party to a construction contract is entitled to payment by installments, stage payments or other periodic payments for any work, unless the contract specifies, or the parties agree, that the work will last less than 45 days. The parties are free to agree the amounts and the intervals. If they do not, the Scheme for Construction Contracts fills the gap.

Section 110 requires every construction contract to provide an adequate mechanism for working out what payments become due and when, and a final date for payment for any sum that becomes due. The parties can agree how long the gap is between the two dates. Since the 2011 amendments, a contract cannot make payment conditional on performance under another contract, and it cannot set the due date by reference to a notice given to the person who is owed money.

The payment notice

Section 110A requires the contract to say that either the payer, or the payee, gives a notice no later than five days after the payment due date. The notice must state the sum considered to be or to have been due at the due date, and the basis on which that sum is calculated. The sum can be zero.

A payment notice is due no later than five days after the payment due date 5 days payment notice: sum considered dueand how it was calculated
NoticeWho gives itMust sayDeadline
Payer’s payment noticeThe payer or a specified personThe sum considered due and how it was calculatedNo later than 5 days after the payment due date
Payee’s payment noticeYou, if the contract requires itThe sum you consider due and how it was calculatedNo later than 5 days after the payment due date
Payee’s default noticeYou, if the payer fails to give theirs on timeThe sum you consider due and how it was calculatedAny time after the payer’s notice was due

Source: Housing Grants, Construction and Regeneration Act 1996, sections 110A and 110B.

A quick map of who sends what, and by when, if your contract follows the Act’s defaults:

StepWhat is sentDeadline
1Payment due dateSet by the contract
2Payment notice stating the sum and calculationNo later than 5 days after the due date
3Pay less notice, if the payer disagreesNo later than the agreed or Scheme period before the final date for payment
4Payment of the notified sum, or the sum in a valid pay less noticeOn or before the final date for payment
5Notice of intention to suspend, if unpaidAt least 7 days before suspending

Source: Housing Grants, Construction and Regeneration Act 1996, sections 110A, 111 and 112.

What happens when the payer is silent

Section 110B covers a payer who was meant to give a notice and did not. You may then give your own notice at any time after the payer’s deadline. The final date for payment of the sum in your notice is postponed by the number of days your notice was late, counted from the payer’s deadline. Section 111(1) then says the payer must pay the notified sum on or before the final date for payment, and the notified sum includes the amount in your notice.

That is the practical value of a clear payment application. If you set out the sum and the calculation and the payer says nothing in time, your number becomes the notified sum.

The pay less notice

A payer who disagrees can give a notice of intention to pay less than the notified sum. Section 111(3) and (4) say the notice must state the sum the payer considers due on the date of the notice and the basis on which it is calculated, and the sum can be zero. Under section 111(5), it must be given no later than the prescribed period before the final date for payment. The parties can agree that period. Without agreement, the Scheme for Construction Contracts sets it.

A payer who disagrees needs a valid pay less notice, given in time with the calculation payment notice withsum and calculation pay less notice,given in time paying less with novalid notice

If a valid pay less notice is given, the payer’s obligation to pay applies only to the sum in that notice. If it is challenged in adjudication and the adjudicator decides more should be paid, section 111(9) says the extra amount is due seven days from the decision or on the original final date for payment, whichever is later.

Suspending work

Section 112 gives you a right to suspend performance if the payer fails to pay a notified sum by the final date for payment. You must first give at least seven days’ notice of your intention to suspend, stating the grounds. The right ends when the payer pays in full, and the payer is liable for a reasonable amount of your costs and expenses caused by the suspension. Any suspension period is disregarded when working out contractual time limits for the affected work.

You must give at least seven days' notice of your intention to suspend work 7 days notice of intention to suspend,stating the grounds

What this means for your invoices

Treat each application for payment as a payment notice if your contract allows it. State the sum, show the calculation, and send it by the date the contract requires, with proof of when it went. Keep your invoice numbering and amounts consistent with the notice so the figures match. A BillyPaid invoice gives you a clean numbered layout with line items, which makes the calculation easy to show.